Project
Al-Dibdibah Power and Al-Shagaya Renewable Energy Phase III Zone 1 Solar PV IPP
KuwaitSolar Energy
A 1,100MW utility-scale solar PV IPP within the Al-Shagaya Renewable Energy Park. Three consortia submitted final technical/commercial proposals: ACWA Power with Alternative Energy Projects Company; Masdar with Fouad Alghanim & Sons; and EDF Renewables with A.H. Al Sagar & Brothers and Korea Western Power (Kowepo). KAPP is the procuring authority; no preferred bidder had been confirmed as of the research cut-off.
Status
ProcurementStatus
RFP issued June 2025; technical/commercial bids received January 2026 from three consortia; financial bids to be opened no later than mid-July 2026; award slipped from an original June 2026 target to Q3 2026; no award confirmed as of the research cut-off (30 September 2026)Procurement Status
Scale & Capacity
1,100 MWNet power capacity
Overview
- Location
- Jahra Governorate, ~100km west of Kuwait City (Al-Shagaya Renewable Energy Park)
- Delivery Model
- 30-year PPA IPP (BOOT: build, own, operate, maintain, transfer)
Participants & Roles
Procuring Authority
Sources