Project
Berwick Bank Wind Farm — Phase B
United KingdomOffshore Wind, Power Generation, Energy Infrastructure, Renewable Energy
Status
Development / PlanningStatus
AwardedProcurement Status
Overview
- Location
- Firth of Forth, Scotland
- Revenue / Payment Model
- Contract for Difference (CfD) — strike price £89.49/MWh (2024 prices, CPI-indexed), 20-year term. Only successful Scottish fixed-bottom CfD award in Allocation Round 7 (Jan 2026).
- Contract Term
- 20 years (CfD)
- Scale / Scope
- On completion, Berwick Bank (all phases) would be the world's largest offshore wind farm. Phase B is the only phase with a secured CfD as of this cut-off; Phases A and C remain unconfirmed, available for future CfD rounds (AR8 expected later in 2026) — not represented as separate records at this stage. Consent was a Scottish Government consent order (July 2025) under the Electricity Act 1989 s.36 / Marine (Scotland) Act 2010 regime, distinct from England's DCO process.
Project Developments
- Project · 14 January 2026SSE secures CfD for Berwick Bank Phase B — only Scottish AR7 award
SSE Renewables secured a Contract for Difference for Berwick Bank Wind Farm Phase B in Allocation Round 7 — the only successful Scottish fixed-bottom offshore wind award in the round. Strike price £89.49/MWh (2024 prices, CPI-indexed), 20-year term.
Participants & Roles
Sponsor / Developer
Government Entity / Grantor
Sources
- SSE plc — investor release, AR7 CfD awardProject Company / Sponsor
- Ofgem — Allocation Round 7 resultsRegulatory / Procurement