Olkaria I Geothermal Power Station Rehabilitation (Units 1–3 Uprate)
KenyaPower Generation, Renewable Energy, Energy Infrastructure
Turbine/generator uprate of Olkaria I Units 1–3 (45MW→63MW). KenGen reported 70% progress; most recent status found was "on track for June 2026" with no confirmed completion or re-commissioning date located as of this review — recorded as Near Completion, not Operational, per Founder Review KE-FR-04 (forecast dates must not become achieved milestones).
Status
Near CompletionStatus
Major Contracts Under DeliveryProcurement Status
Overview
- Location
- Olkaria, Kenya