Programme
Presidential Power Initiative (Siemens Grid Programme)
NigeriaElectricity Transmission, Grid Infrastructure, Energy Infrastructure
Federal transmission-strengthening programme with Siemens as technology/EPC partner. Independently confirmed as delivered: 10 mobile substations delivered (7 installed) and 10 transformers connected to the grid, adding an estimated ~984MW of wheeling capacity. Two of five further substations under construction (Abeokuta, Ayede, Onitsha specifically named) are targeted for completion by December 2026 — forecast. The programme's own restated 25,000MW target is treated with explicit skepticism, never as achieved or imminent.
Status
ImplementationStatus
Major Works Under Delivery / Programme Reset OngoingProcurement Status
Scale & Capacity
10 unitsMobile substations delivered
7 unitsMobile substations installed
10 unitsTransformers connected to grid
Overview
- Location
- Multi-state, Nigeria (federal programme)
- Scale / Scope
- Federal transmission-strengthening programme, originally conceived August 2018 (Buhari-Merkel meeting), executed in partnership with Siemens under FGN Power Company. Publicly restated/"revived" multiple times, most recently a November 2025 presidential fast-track statement. Represented as one programme record, not fragmented into individual substation/transformer installations. The programme's own repeatedly restated 25,000MW capacity target is explicitly NOT treated as an achieved or near-term figure.
Participants & Roles
Technology / Equipment Provider
Utility / Network Operator
Sponsor / Developer
Sources
- Federal Ministry of Information and National Orientation / State House — PPI substation progressOfficial / Government
- Transformer-technology.com — PPI Phase 1 technical progressIndustry / Trade Source