Law & Regulation

Preferential Procurement Regulations, 2022

South AfricaPublic ProcurementIn Force

Prescribes how organs of state within the PPPFA framework apply the 80/20 and 90/10 preference-point systems: the value threshold dividing the systems, price-scoring formulas, tender-invitation disclosure requirements, and treatment where a tender's value is unclear at invitation stage. Commenced 16 January 2023, replacing the invalidated 2017 Regulations. Remains part of the operative framework as at the research cut-off; the uncommenced 2024 Public Procurement Act and draft 2026 regulations do not yet displace it.

Key Provisions

  • Regulation 2 — Application

    Applies the Regulations within the PPPFA framework and requires an organ of state to determine its preferential procurement policy. Practical consequence: obtain the current policy and tender terms — the Regulations are not a complete institution-specific policy.

  • Regulation 3 — Identification of system and goals

    Requires the tender invitation to stipulate the applicable preference system and specific goals, with points allocated to each. Practical consequence: goals and evidence should not be created or materially changed after bids are submitted.

  • Regulation 4 — 80/20 system

    Prescribes the price formula and allocation of points for tenders at or below the stated Rand-value threshold. Practical consequence: bidders can model the commercial effect of price movement and available goal points.

  • Regulation 5 — 90/10 system

    Prescribes the price formula and allocation of points for tenders above the stated threshold. Practical consequence: price carries greater relative weight for larger procurements, including many infrastructure packages.

  • Regulation 6 — Unclear tender value

    Provides a process where the estimated value cannot be determined at invitation stage and the appropriate system becomes known after evaluation. Practical consequence: tender documents should explain the possible systems.

  • Regulations 4–6 — Price definition and scoring base

    Regulates comparative price calculations, including price after unconditional discounts where applicable. Practical consequence: commercial schedules and discounts must be drafted so the scored price is clear and auditable.

  • Tender-specific provisions — Specific goals

    Leaves institutions to identify lawful specific goals under their policy and allocate the prescribed maximum points in the invitation. Practical consequence: do not assume B-BBEE is the only possible goal or that the same points apply across authorities.

  • Evidence provisions — Proof of claimed goals

    Requires claims to be supported in the manner stated by the procuring institution and governing framework. Practical consequence: validate evidence across consortium members before bid submission.

  • Award provisions — Highest-point tender and objective criteria

    Operates with PPPFA section 2's general award rule and lawful objective-criteria exception. Practical consequence: a departure from ranking requires a defensible statutory basis and decision record.

  • Remedy provisions — False information and non-compliance

    Supports action where a bidder obtained preference through false information, subject to lawful process. Practical consequence: authorities should monitor material claims; contractors should retain substantiation.

InfraLex Relevance

The current operative detail beneath the PPPFA, translating the statute's preference architecture into bid-level scoring while preserving institution-specific policy choice — analysed separately from the expired 2017 provisions and the uncommenced future framework.

Instrument Overview

Official Citation
Government Notice 2721 of 2022; Government Gazette 47452, 4 November 2022
Instrument Type
Regulation
Source Language
English
Enactment Date
4 November 2022
Effective Date
16 January 2023
Last Verified
6 September 2026

Official Source

View official source ↗